a.m. wrote:Fixed. Please see changeset
3f7a64c00e72. Thanks again for reporting
Hi Andrei,
I think it is still not working with nopCommerce 3.7.
A scheduled task is running at random. Not considering the "Last success date". The value for "Seconds (run period)" is set to 86400.
When the task runs it creates an information log called "Data import started" and another log called "Data import Completed".
See the following logs:
Log level Short message Created on ViewInformation Data import completed 7/5/2017 8:22:41 PM View
Information Data import started
7/5/2017 8:22:41 PM View
Information Application started 7/5/2017 8:17:41 PM View
Information Application started 7/4/2017 8:57:49 PM View
Information Application started 7/4/2017 8:13:15 PM View
Information Application started 7/4/2017 2:57:27 PM View
Information Data import started
7/4/2017 9:50:43 AM View
Information Application started 7/3/2017 9:50:43 AM View
Information Data import completed 7/3/2017 4:35:05 AM View
Information Data import started
7/3/2017 4:35:05 AM View
Information Application started 7/2/2017 4:35:05 AM View
Information Data import completed 7/1/2017 10:15:04 PM View
Information Data import started
7/1/2017 10:15:04 PM View
Information Data import completed 6/30/2017 11:25:42 PM View
Information Data import started
6/30/2017 11:05:10 PM View
As per the log the process run at 6/30/2017 11:05:10 PM and then expected to run after 24hrs but it ran in 23hrs. The third run was 30hrs from the second run. The server and the site was online all the time.
Any idea what might be causing the issue?